Developer-led · Rotherham town centre

Bridge Court

A storage building near Forge Island turned into six commercial and light-industrial units.

Bridge Court: Unit 5 after completionApproved first time
LocationRotherham town centre
TypeDeveloper-led
BeforeStorage building (Class B8)
After6 units (Class E and B2)
Planning routeFull planning
Units6
Consent9 weeks
OutcomeFirst time
StatusApproved first time

Photos and drawings

The hard part

Making the layout work: getting the most usable, lettable units out of the existing building.

What we did

We set out a clear strategy early, which made the layout and the planning case straightforward. Consent came in nine weeks, first time.